Project Timeline

 

  • TM Vote 10/19/10 (allowed FPL to apply for grant and receive funds)
  • TM Vote 1/13/11 (approved plan; approved purchase of site)
  • Grant Submitted 1/27/11
  • Grant Notification 7/14/11
    The new McAuliffe branch is sixth on the waiting list of 15
  • Provisional Grant awarded 10/4/12
  • Request funding from Town Meeting 4/13
  • Sign contract with the MBLC when the funds are approved
  • Purchase the land using MBLC funds by 6/13
  • Architect Prepares Final Plan
  • Select contractor – date TBD
  • Begin construction – date TBD